PROJECT
Lagoon Sludge Dredging for Rio Tinto Alcan
SERVICE
INDUSTRY
Manufacturing
PROJECT LOCATION
PROJECT DATE
June 2022
QUANTITY
2,375 m3 of water treated
CHALLENGES
A 20,000 m3 sedimentation lagoon had to be dredged and the water from the dredging had to be treated to lower its fluoride and aluminum content 6 days a week, 24 hours a day, in order to keep pace with the dredging.
BACKGROUND
In June 2022, Rio Tinto Alcan and the engineering consulting firm BBA contacted SANEXEN to urgently treat the water resulting from the dredging of sludge from the sedimentation lagoon located at the end of the Rio Tinto Alcan process plant in Laterrière, Saguenay, Quebec.
SOLUTION
Implementation of the treatment process tested in the laboratory by BBA withing 2 months, and design and mobilization of a mobile treatment plant with a treatment capacity of 35 m3/h of contaminated water.
Monitoring of the process program and quality of the treated water, in accordance with the customer’s requirements. The treatment objectives set by Rio Tinto Alcan were 20 mg/l total fluoride and 1.5 mg/l total aluminum. The treated water was analyzed on site twice every 12-hour shift and was also analyzed by an accredited laboratory over a 24-hour period to verify its quality.
The following technologies were used:
- Decantation
- Defluoruration by the Nalgonda method (addition of lime milk)
- Coagulation
- Neutralisation with addition of acid
- Aluminum chelation (MetalsorbTM)
- Filtration
- Fluorine adsorption on activated alumina
The dredged water and sludge from the sedimentation lagoon was centrifuged and the water was sent directly to the primary decantation tank of the water treatment process. The addition and mixing of the chemical reagents was done directly in the pipes using a mobile and compact mixing coil assembly designed specifically for this project. Secondary decantation took place in a tank immediately after mixing, avoiding the release of sludge into the tank during maintenance. The treated water was then returned to the sedimentation tank.
A total volume of 2,375 m3 of contaminated water was treated during the project.
INTERESTED IN WORKING WITH US?
Contact us to learn more.
SEE SIMILAR PROJECTS
Removing Dry Tons from Texas Water Treatment Lagoons
PROJECTSERVICESDredging and Dewatering Biosolids ManagementINDUSTRYMunicipalPROJECT LOCATIONTexasPROJECT DATE2022QUANTITY200,000 dry tonnes of sludge dredgedCHALLENGESRemove up to 200,000 dry tons from two water treatment backwash lagoons. Lagoon 1 was no longer in...
Dredging, Dewatering and Transportation of Pulp Mill ASB Wastewater Sludge
PROJECTSERVICEDredging and Dewatering Biosolids ManagementINDUSTRYPulp & PaperPROJECT LOCATIONAlbertaPROJECT DATE2015-2023QUANTITY10,000 dry tonnes of wastewater solids removedCHALLENGESDredging, dewatering and transporting up to 10,000 dry tonnes of pulp mill...
Digester Cleaning with Significant Sand and Solids Build-up in California
PROJECTSERVICEDredging and Dewatering Biosolids ManagementINDUSTRYManufacturingPROJECT LOCATIONSouthern CaliforniaPROJECT DATE2020-2025QUANTITY350 million gallons/day of wastewater treatedCHALLENGESCleaning up to 30 digesters over a 5-year period from 2 plants in...