Biosolids Management

Dredging & Dewatering

Flexible Fluid Transport Solutions

Industrial Effluents Treatment

Lead Free Solutions

PFAS Removal Solutions

Water Main Renewal

Construction & Demolition Fines Recycling

Environmental Site Remediation

Industrial Degraded Sites Management

Regulated Materials Management

Risk Assessment

Soil and Material Management

PROJECT

Digester Cleaning with Significant Sand and Solids Build-up in California

SERVICE
INDUSTRY

Manufacturing

PROJECT LOCATION

Southern California

PROJECT DATE

2020-2025

QUANTITY
350 million gallons/day of wastewater treated
CHALLENGES
Cleaning up to 30 digesters over a 5-year period from 2 plants in southern California historically known to have significant sand and solids build-up making it difficult to dewater. APG’s challenge was to meet the client’s cleaning schedule, which involved moving equipment to different locations within each plant, and sometimes plant to plant.
BACKGROUND
The client has two plants in southern California. Plant 1 treats up to 200 million gallons of wastewater each day and has 12 large digesters. Plant 2 treats up to 150 million gallons of wastewater each day with several, smaller digesters located right at the Pacific Ocean shore. More than 2.5 million people are serviced in the southern California area.
SOLUTION

APG approached cleaning the digesters at both plants the same as we do with all digesters. While not having a clear understanding as to how this work was completed in the past, APG has been able to clean the digesters in less time and has completed the work to date ahead of the client’s desired schedule and quicker than any competitors have done in the past.

After APG was awarded the project, the client requested a change: taking the dewatered solids to beneficial reuse locations rather than a landfill. APG was able to identify a compost facility that would accept the material and change the transportation contractor with minimal effect on schedule, and with a reasonable increase the client was willing to accept. APG is continuing to identify other compost facilities to accept the dewatered material to provide redundancy for the end use of the dewatered solids. This allows the material to be reused beneficially as opposed to taking up space in a landfill, which was a big win for the client.

INTERESTED IN WORKING WITH US?

Contact us to learn more.

SEE MORE SIMILAR PROJECTS

Removing Dry Tons from Texas Water Treatment Lagoons

Removing Dry Tons from Texas Water Treatment Lagoons

PROJECTSERVICESDredging and Dewatering Biosolids ManagementINDUSTRYMunicipalPROJECT LOCATIONTexasPROJECT DATE2022QUANTITY200,000 dry tonnes of sludge dredgedCHALLENGESRemove up to 200,000 dry tons from two water treatment backwash lagoons. Lagoon 1 was no longer in...

read more